Co-Op Student Evaluation Project
Meeting Minutes - 03/21/05
- Addition to form
-
After the Iteration 3 checkpoint is delivered, we are only going to have minor
modifications to the system - there will be no major changes
- Testing focus
-
Dr. Contomanolis emphasized that it is very important for this project to have everything
working as specified when deploying the system.
- User and installation manuals
- Should add notes about default behavior
-
The data in the "Approved" column should be Yes/No rather than a bullet
- Need to remove the hour from the last update dates
- Add "All" option to departments search criteria
-
We are planning on discussing whether or not we want to change the student view page
to a row-based layout (rather than the current layout) at our next meeting.
-
Dr. Contomanolis stated that he doesn't like the idea of testing a new system by
forcing end users to use it