This was the second week of Iteration 3. We started the week with another meeting with our stakeholders in which we showed
continued refinements in the administrative and faculty side in terms of searching for reports/evaluations and the integration of the student
and employer functionality. This elicited a lot of good feedback and may lead to showing new functionality every week. We are stil focusing on getting
reporting done and hope to have a near feature-complete system by the end of Iteration 3. In addition, we have spent some time refining our
documents so they can be brought along gradually.
Individual Tasks and Accomplishments
- Chris - Fixed backend to support single form
- Dan - Made appropriate fixes for the deploy
Issues to Resolve
- Develop schedule/plan for Iteration 4.
Short Plan for Next Week
- Finish Iteration 3, and determine fine-grained goals for Iteration 4.