jTIGRESS Project Plan & Tracking





Project Start:
Project Finish:
Mon 12/1/03
Fri 5/21/04


Milestones (Estimated)


ID
Task Name
DurationStartFinish% Complete
1
Portal Document
110 days Mon 12/1/03 Fri 5/21/04 100%
2
Web Page
110 days Mon 12/1/03 Fri 5/21/04 100%
3
Hardware/Software Installs
21 days Mon 12/1/03 Sun 12/21/03 100%
4
Process Document
14 days Mon 12/15/03 Sun 12/28/03 100%
5
Workstation Configuration
14 days Mon 1/5/04 Sun 1/18/04 100%
6
TIGRESS Intro Research
14 days Mon 1/5/04 Sun 1/18/04 100%
7
Portal Research & Development
21 days Mon 1/19/04 Sun 2/8/04 100%
8
First Prototype
14 days Mon 2/2/04 Sun 2/15/04 100%
9
First Presentation
7 days Mon 2/16/04 Sun 2/22/04 100%
10
Objectives Elicitation
5 days 3/8/04 3/12/04 100%
11
Design / Planning
5 days 3/15/04 3/19/04 100%
12
Design Prototype / Planning Finalize
5 days 3/22/04 3/26/04 100%
13
Iterative Period 1
2 days 3/27/04 3/28/04 100%
14
Feedback / Development 1
5 days 3/29/04 4/3/04 100%
15
Iterative Period 2
8 days 4/4/04 4/11/04 100%
16
Feedback / Development 2
5 days 4/11/04 4/15/04 100%
17
Final Iterative Period
10 days 4/16/04 4/25/04 100%
18
Final Documentation / Workshop
24 days 4/26/04 5/20/04 100%
19
Presentation
13 days 5/8/04 5/20/04 100%

Assignments (Actual)


Task IDTask NameResource NameWork RemainingStartFinish% Work Complete
1 Portal Document Jon P.(manager), All Maintenance Fri 1/16/04 - 75%
2 Web Page Chris Maintenance Mon 12/1/03 Fri 5/21/04 75%
3 Hardware/Software Installs Greg - Mon 12/1/03 Mon 1/26/04 100%
4 Process Document All - Mon 12/15/03 Sun 1/8/04 100%
6 TIGRESS Research Greg - Mon 1/5/04 - 100%
8 Simple Portlet Sample Chris & Jon F. - 1/26/04 1/29/04 100%
8 Message Sending Portlet Sample Chris, Jon F., Jon P. - 2/2/04 2/5/04 100%
9 Presentation Jon F. (manager), All - 2/9/04 2/16/04 100%


SEE EXCEL SPREADSHEET FOR PHASE 2 TIMES