- Last meeting before scheduled code delivery and final presentations
- Discussed final steps of the project
- Showed final version of poster to be shown the following day at the IAB event
Back to top
- Authentication
- OCECS may need to modify authentication system if ldap is desired to be used
- Test suite subject to data change
- Placement bugs found are in the processes of being corrected
- All methods will use the 5-digit quarter format for consistency
Back to top
- Reviewed status of placement service
- going to make parameters cleaner
- stored procedures used by placement needs to make years in 20071 format instead of current 071 format
- Authorization catches all service requests
- Activity service not returning data on production box
- data is in the database
- appears the view is not being populated on production box
- on test box the stored procedue doesn't exist
- need to further investigate this issue
- Went over testing goals
- automatic testing of every service method
- data quality will be assured in the automated tests
- Poster
- no specific requirements from the customer
- poster will emphasize benefits of the design (since our project is about the architecture of the new system)
- Need to follow up on ITS/Financial aid discussion
- Professor Ludi has master's students analyzing our project
- will see about getting them a dump of our bug tracker and course code
Back to top
- discussed with co-ops the service implementation
- got feedback about what we have coded so far
- answered questions they had
- updated customer on our progress
- answered any concerns the customer had regarding our progress
Back to top
- Showed current progress of service implemenation
- Discussed implementation plans with the co-ops
- Brought Dan up to speed on project progress since our last meeting
- Covered odds and ends in need of addressing
Back to top
- Got SVN configured so it commits directly to wwwroot
- Went over class diagram and WSDL documents
- Updated progress of service development
- Discussed next steps team will be taking
- Scheduled meeting times with co-ops (career fair limits availability)
Back to top
- Spring Co-op Status
- Phil
- New Co-op (John)
- UI developer
- Ken part time (4 hours/week)
- Test Server
- Phil is looking at login issue
- Phil will ask about version control by Friday 22 morning
- tentatively - SVN on test server
- Place ticket as reminder
- Deployment/transition
- Phase in with current system
- Phil checks with office if there is any existing plan/idea
Back to top
- Explained architecture model and discussed requirements with Manny
- Reviewed SRS document with Ken and Phill
- Discussed comments made by Jim in SRS document
- Dicussed system authentication and how it will secure the web services
Back to top
- covered the issue of VS on the dev box (ended up being a non-issue)
- reviewed the modified architecture document
- will focus on web pages as the primary consumer of the services
- still keep to SOAP standard to allow for possibility of other non-web clients
- will work with Ken and Phil on the authorization contract to allow for secure access (ticket no.20)
- architecture will allow for addition of 'custom services' that can make use of lower level services (student, employer, etc.)
- covered the addition of database pooling for speed optimization
- update for next week to reflect full authorization model and how other services can fit in
- discussed other possibilites of speed optimization
- database indexing - something that team will look into as part of this project
- use of current compiled tables or views
- as long as they are already created, the risk of out of date data is acceptable
- if team creates new views/tables we must research as to how often they are updated
- caching - out of scope for project, but still possible after completion
- covered features/access points for placement service
- add in the possibility for filtering of international placements
- can combine the summary and detailed views for the student report
- agreed upon all other mentioned access points
- discussed some of the other possible services such as alerts
- team needs a requirements doc to fully describe all features that are in the scope of this project
Back to top
- resolved database access issue
- Review user stories, sequence diagrams, and state machine
- Review updated architecture
- Interim presentation time finalized
- Brainstormed with Co-ops on XML format
Back to top
- Discussed high level architecture of system
- Analyzed several use-cases
- Group discussion of system components
Back to top
- Discussed test server:
- MS SQL Server 2000 & 2005
- Develop on Drive E: (aka SETeam folder)
- Project Plan:
- Will send updated copy this weekend
- Discussed Deadlines, Sprints, and Metrics (code and document
metrics)
- Discussed Queries:
- Standard overall in time
- Biggest and slowest is when you find out everything from a person or a company
- Placement table the most important / recommended starting point
- Job Zone:
- We have accounts on it now.
Back to top
- Reviewed draft project plan with customer
- explained project process
- defined project scope
- approved web services proposal
- Outlined project schedule
- planned for 2 week early completion requirement
- Discussed metrics to be collected
- Explained test server needs, Co-op Office is getting the server setup
Back to top
- Discussed the system to be developed in further detail
- more technical talk
- went over current web service design in prototype built by Ken, their current co-op employee
- Customer provided database schema and screen shots of the current system
- Provided access with internal bug tracker
- Started process of obtaining a test server and database
Back to top
- Initial kick off meeting
- Discussed system to be developed
- Gathered high level requirements and performed a quick walk through of the current system
Back to top