Out Cold - Project Metrics
Process Metrics
Slippage
( Actual Progress / Planned Progress ) - 1 Progress measurements are in week amounts. Taken at T/R meetings. Team / Individual Estimation Bias ( Estimated Time / Actual Time ) - 1 Time measurements are taken in hours. Team Focus Diversions / Meeting Hour Diversions are defined as non-project discussion threads brought up during meetings. Team / Individual Task Domain Effort Effort spent in one task domain / total weekly hours |
Technical Metrics
Note: These will be automated as much as possible using existing technologies. This list will be updated once we settle on a development / testing environment, and see what can be easily gathered and automated.
Test Efficiency Test Coverage / Defects Logged Requirements
Requirements Volatility
Number of Requirements Changes (Weekly) / Total Number of Requirements To be taken weekly during initial phases of project (when requirements are certain to be forming and changing), and later during the project during weeks in which requirements are updated. |