E911 Development Schedule
|
Weeks 1-3 |
Review existing system and documentation |
Week 3 |
Create Project Plan |
Weeks 4-8 |
Gather Requirements / Deliver Requirements Document |
Week 7-8 |
Create and Deliver Revised Data Model |
Week 9-10 |
Architecture & Design Document |
Week 11 |
Begin Implementation |
Week 13 |
Begin Unit Testing / Alpha Release |
Week 17 |
Beta Release |
Week 18 |
Software Complete |
Week 19 |
Conclude Testing |
Week 20 |
Deliver Final Product, Presentation & Post Mortem |
Color
Denotes Deliverables |