Team Spy Penguins
Weekly Report – January 30, 2009
Major Deliverables
Requirement Specification Document
- Second Revision was reviewed of BRS and was team was given the go to start on the SRS
- SRS was placed into BRS document and they are now called Requirement Specification Document.
Major Accomplishments
Team reviewed next revision of BRS with sponsors and then started SRS. SRS revision should be completed by Saturday January 31, 2009. Team started working on UI Prototypes and discussed mid-term presentation. We also worked out how we wanted to design our definition language and added the idea of a Conditional Element.
Concerns/Risks
-Design might not fully be completed by presentation time.