Task Actual Schedule Slip First Estimate Revised Estimate 1 Note: All effort times are in hours.
Mid-Project Presentation 7 6 8
Final Presentation 9 15
Project Poster 6 7
Technical Report 3 8
Post-Mortem Reflection 4 5
BRS 95 5 days 10 46
SRS 13 10 40
Risk Management Document 10
Project Plan 37 6
Architecture Document 13 15 20
Design Document 3 15 20
Test Plan 12 20
Review Requirements and Risks (Stage 1) 2 2
Design modifications 6
UI Prototyping 12 6 10
Design UI and web architecture 13 20
Examine PAETEC examples 8 20
Research and decide on definition method 4 5
Design master definition 15 30
Implementation (Stage 1) 40 100
Testing (Stage 1) 5 10
Bug fixes (Stage 1) 10 20
Release (Stage 1) 3 12
Research UI tools 10 20
Review Previous release (Stage 2) 4 4
Modify Requirements and schedule (Stage 2) 2 2
Review Design 6
Implementation (Stage 2) 50 150
Usability 2 10
Testing (Stage 2) 5 10
Bug fixes (Stage 2) 10 10
Release (Stage 2) 5 12
Review Previous release (Stage 3) 4 4
Modify Requirements and schedule (Stage 3) 2 2
Design exporting modules 3 30
Implementation (Stage 3) 25 150
Test and verify output 10 30
Bug fixes (Stage 3) 15 20
Prepare final release 10 12