Category Task  Completion Projected Time (hrs) Projected Start Date Projected End Date Actual Time(hrs) Actual Start Date Actual End Date Non Negotable End Date? Predecessors Rescource   Estimation Accuracy                                                                                                                                                                                                
                                                                                                                                                                                                                           
Agenda Agenda Week 1 100.00% 1 12/2/08 12/2/08 1 12/2/08 12/2/08 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 2 100.00% 1 12/9/08 12/9/08 1 12/9/08 12/9/08 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 3 100.00% 1 12/16/08 12/16/08 1 12/16/08 12/16/08 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 4 100.00% 1 1/5/09 1/5/09 1 1/5/09 1/5/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 5 100.00% 1 1/12/09 1/12/09 1 1/12/09 1/12/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 6 100.00% 1 1/19/09 1/19/09 1 1/19/09 1/19/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 7 100.00% 1 1/26/09 1/26/09 1 1/26/09 1/26/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 8 100.00% 1 2/2/09 2/2/09 1 2/2/09 2/2/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 9 100.00% 1 2/9/09 2/9/09 1 2/9/09 2/9/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 12 100.00% 1 3/9/09 3/9/09 1 3/9/09 3/9/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 13 100.00% 1 3/16/09 3/16/09 1 3/16/09 3/16/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 14 100.00% 1 3/23/09 3/23/09 1 3/23/09 3/23/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 15 100.00% 1 3/30/09 3/30/09 1 3/30/09 3/30/09 Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 16 100.00% 1 4/6/09 4/6/09       Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 17 100.00% 1 4/13/09 4/13/09       Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 18 100.00% 1 4/20/09 4/20/09       Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 19 100.00% 1 4/27/09 4/27/09       Yes   Phil                                                                                                                                                                                                    
Agenda Agenda Week 20 100.00% 1 5/4/09 5/4/09       Yes   Phil                                                                                                                                                                                                    
                                                                                                                                                                                                                           
Sponsor Meetings Meeting With Sponsor Week 1 100% 1.5 12/2/08 12/2/08 1.5 12/2/08 12/2/08     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 2 100% 1.5 12/9/08 12/9/08 1.5 12/9/08 12/9/08     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 3 100% 1.5 12/16/08 12/16/08 1.5 12/16/08 12/16/08     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 4 100% 1.5 1/6/09 1/6/09 1.5 1/6/09 1/6/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 5 100% 1.5 1/13/09 1/13/09 1.5 1/13/09 1/13/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 6 100% 1.5 1/20/09 1/20/09 1.5 1/20/09 1/20/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 7 100% 1.5 1/27/09 1/27/09 1.5 1/27/09 1/27/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 8 100% 1.5 2/3/09 2/3/09 1.5 2/3/09 2/3/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 9 100% 1.5 2/10/09 2/10/09 1.5 2/10/09 2/10/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 12 100% 1.5 3/10/09 3/10/09 0 3/10/09 3/10/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 13 100% 1.5 3/17/09 3/17/09 1.5 3/17/09 3/17/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 14 100% 1.5 3/24/09 3/24/09 1 3/24/09 3/24/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 15 100% 1.5 3/31/09 3/31/09 0.5 3/31/09 3/31/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 16 100% 1.5 4/7/09 4/7/09 1 4/7/09 4/7/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 17 100% 1.5 4/14/09 4/14/09 1 4/14/09 4/14/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 18 100% 1.5 4/21/09 4/21/09 1 4/21/09 4/21/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 19 100% 1.5 4/28/09 4/28/09 0 4/28/09 4/28/09     Team                                                                                                                                                                                                    
Sponsor Meetings Meeting With Sponsor Week 20 100% 1.5 5/5/09 5/5/09 1 5/5/09 5/5/09     Team                                                                                                                                                                                                    
                                                                                                                                                                                                                           
Meeting Minutes Meeting Minutes Week 1 100% 2 12/3/08 12/3/08 2 12/3/08 12/3/08 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 2 100% 2 12/10/08 12/10/08 2 12/10/08 12/10/08 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 3 100% 2 12/17/08 12/17/08 2 12/17/08 12/17/08 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 4 100% 2 1/7/09 1/7/09 2 1/7/09 1/7/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 5 100% 2 1/14/09 1/14/09 2 1/14/09 1/14/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 6 100% 2 1/21/09 1/21/09 2 1/21/09 1/21/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 7 100% 2 1/28/09 1/28/09 2 1/28/09 1/28/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 8 100% 2 2/4/09 2/4/09 2 2/4/09 2/4/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 9 100% 2 2/11/09 2/11/09 2 2/11/09 2/11/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 12 100% 2 3/11/09 3/11/09 0 3/11/09 3/11/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 13 100% 2 3/18/09 3/18/09 1 3/18/09 3/18/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 14 100% 2 3/25/09 3/25/09 1 3/25/09 3/25/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 15 100% 2 4/1/09 4/1/09 2 4/1/09 4/1/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 16 100% 2 4/8/09 4/8/09 1 4/8/09 4/8/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 17 100% 2 4/15/09 4/15/09 1 4/15/09 4/15/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 18 100% 2 4/22/09 4/22/09 1 4/22/09 4/22/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 19 100% 2 4/29/09 4/29/09 1 4/29/09 4/29/09 Yes   Rob                                                                                                                                                                                                    
Meeting Minutes Meeting Minutes Week 20 100% 2 5/6/09 5/6/09 1 5/6/09 5/6/09 Yes   Rob                                                                                                                                                                                                    
                                                                                                                                                                                                                           
Website Upkeep Website Upkeep Week 1 100% 2 12/5/08 12/5/08 2 12/5/08 12/5/08     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 2 100% 2 12/12/08 12/12/08 2 12/12/08 12/12/08     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 3 100% 2 12/19/08 12/19/08 2 12/19/08 12/19/08     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 4 100% 2 1/9/09 1/9/09 2 1/9/09 1/9/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 5 100% 2 1/16/09 1/16/09 2 1/16/09 1/16/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 6 100% 2 1/23/09 1/23/09 2 1/23/09 1/23/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 7 100% 2 1/30/09 1/30/09 2 1/30/09 1/30/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 8 100% 2 2/6/09 2/6/09 2 2/6/09 2/6/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 9 100% 3 2/13/09 2/13/09 2 2/13/09 2/13/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 10 100% 2 2/20/09 2/20/09 2 2/20/09 2/20/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 11 100% 2 2/27/09 2/27/09 2 2/27/09 2/27/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 12 100% 2 3/13/09 3/13/09 2 3/13/09 3/13/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 13 100% 2 3/20/09 3/20/09 2 3/20/09 3/20/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 14 100% 2 3/27/09 3/27/09 2 3/27/09 3/27/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 15 100% 2 4/3/09 4/3/09 2 4/3/09 4/3/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 16 100% 2 4/10/09 4/10/09 2 4/10/09 4/10/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 17 100% 2 4/17/09 4/17/09 2 4/17/09 4/17/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 18 100% 2 4/24/09 4/24/09 2 4/24/09 4/24/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 19 100% 2 5/1/09 5/1/09 2 5/1/09 5/1/09     Tom                                                                                                                                                                                                    
Website Upkeep Website Upkeep Week 20 100% 2 5/8/09 5/8/09 2 5/8/09 5/8/09     Tom                                                                                                                                                                                                    
                                                                                                                                                                                                                           
Effort Tracking Effort Tracking Week 1 100% 1 12/5/08 12/5/08 1 12/5/08 12/5/08 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 2 100% 1 12/12/08 12/12/08 1 12/12/08 12/12/08 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 3 100% 1 12/19/08 12/19/08 1 12/19/08 12/19/08 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 4 100% 1 1/9/09 1/9/09 1 1/9/09 1/9/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 5 100% 1 1/16/09 1/16/09 1 1/16/09 1/16/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 6 100% 1 1/23/09 1/23/09 1 1/23/09 1/23/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 7 100% 1 1/30/09 1/30/09 1 1/30/09 1/30/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 8 100% 1 2/6/09 2/6/09 1 2/6/09 2/6/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 9 100% 1 2/13/09 2/13/09 1 2/13/09 2/13/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 10 100% 1 2/20/09 2/20/09 1 2/20/09 2/20/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 11 100% 1 2/27/09 2/27/09 1 2/27/09 2/27/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 12 100% 1 3/13/09 3/13/09 1 3/13/09 3/13/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 13 100% 1 3/20/09 3/20/09 1 3/20/09 3/20/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 14 100% 1 3/27/09 3/27/09 1 3/27/09 3/27/09 Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 15 100% 1 4/3/09 4/3/09       Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 16 100% 1 4/10/09 4/10/09       Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 17 100% 1 4/17/09 4/17/09       Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 18 100% 1 4/24/09 4/24/09       Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 19 100% 1 5/1/09 5/1/09       Yes   Team                                                                                                                                                                                                    
Effort Tracking Effort Tracking Week 20 100% 1 5/8/09 5/8/09       Yes   Team                                                                                                                                                                                                    
                                                                                                                                                                                                                           
  Project Plan Document 100% 6 12/11/08 12/17/08 37 12/11/08 1/22/09     Team   616.67%                                                                                                                                                                                                
Requirements BRS Document 100% 46 1/5/09 1/9/09 68 1/5/09 1/15/09     Team   147.83%                                                                                                                                                                                                
Requirements Risk Management Document 100% 10 1/12/09 1/13/09   1/12/09 1/13/09     Team   0.00%                                                                                                                                                                                                
Requirements Risk Management Document Upkeep 100% 6 1/13/09 5/20/09   1/13/09     Risk Management Document Team   0.00%                                                                                                                                                                                                
Requirements Examine PAETEC Examples 100% 20 1/9/09 1/12/09 4 1/9/09 1/12/09     Team   20.00%                                                                                                                                                                                                
Requirements SRS Document 100% 58 1/25/09 1/31/09 44 1/25/09 1/31/09   Revise BRS Team   75.86%                                                                                                                                                                                                
Requirements UI Prototyping 100% 20 2/5/09 2/6/09 4 2/5/09 2/6/09   Revise SRS Team   20.00%                                                                                                                                                                                                
Requirements Decide on Definition Method 100% 3 1/29/09 1/29/09   1/29/09 1/29/09     Team   0.00%                                                                                                                                                                                                
  Mid Project Presentation: Coordinate With Sponsor 100% 1 4/16/09 4/16/09 2 4/16/09 4/16/09     Team   200.00%                                                                                                                                                                                                
Design Design Master Definition 100% 30 2/7/09 3/6/09 14 2/7/09 3/13/09   Requirements Team   46.67%                                                                                                                                                                                                
Design Design UI and Web Architecture 100% 20 2/7/09 3/6/09 12 2/7/09 3/6/09   Requirements Team   60.00%                                                                                                                                                                                                
Design Design Document 100% 55 2/9/09 3/6/09 53 2/9/09     Requirements Team   96.36%                                                                                                                                                                                                
Design Architecture Document 100% 20 2/10/09 2/18/09 10 2/10/09 2/25/09   Requirements Team   50.00%                                                                                                                                                                                                
Design Test Plan 100% 28 3/4/09 3/6/09 14 3/4/09 3/15/09   Requirements Team   50.00%                                                                                                                                                                                                
  Mid Project Presentation: Draft 100% 6 2/8/09 2/8/09 24 2/8/09 2/8/09     Team   400.00%                                                                                                                                                                                                
  Week 10 Deliverables 100% 3 2/16/09 2/16/09 0 2/16/09 2/16/09 Yes   Team   0.00%                                                                                                                                                                                                
  Mid Project Presentation 100% 1 2/17/09 2/17/09 2 2/17/09 2/17/09 Yes   Team   200.00%                                                                                                                                                                                                
  Spring Week 1 State of Project 100% 3 3/14/09 3/14/09 2 3/14/09 3/14/09 Yes   Team   66.67%                                                                                                                                                                                                
  Week 11 Reflections 100% 4 3/14/09 3/16/09 2 3/14/09 3/16/09 Yes   Team   50.00%                                                                                                                                                                                                
Release 1 Modify Requirements 100% 2 3/7/09 3/8/09 2 3/9/09 3/18/09   Requirements Team   100.00%                                                                                                                                                                                                
Release 1 Research UI Tools 100% 20 3/7/09 4/4/09 0         Team   0.00%                                                                                                                                                                                                
Release 1 Design modifications 100% 6 3/16/09 3/16/09 8 3/17/09     Design Document Team   133.33%                                                                                                                                                                                                
Release 1 Implementation 100% 173 3/18/09 4/3/09 102 3/14/09 4/4/09     Team   58.96%                                                                                                                                                                                                
Release 1 Testing 100% 20 4/4/09 4/9/09 37 4/4/09     Implementation Team   185.00%                                                                                                                                                                                                
Release 1 Bug Fixes 100% 20 4/6/09 4/10/09 10       Implementation Team   50.00%                                                                                                                                                                                                
Release 1 Create Source Package 100% 2 4/11/09 4/11/09 3       Bug Fixes Team   150.00%                                                                                                                                                                                                
Release 1 Release Notes 100% 4 4/11/09 4/11/09 3         Team   75.00%                                                                                                                                                                                                
Release 1 Deployment Instructions 100% 6 4/12/09 4/13/09 2       Bug Fixes Team   33.33%                                                                                                                                                                                                
Release 2 Review Previous Release 100% 4 4/11/09 4/11/09 4         Team   100.00%                                                                                                                                                                                                
Release 2 Review Design 100% 6 4/11/09 4/11/09 3       Design Document Team   50.00%                                                                                                                                                                                                
Release 2 Modify Requirements/Schedule 100% 2 4/11/09 4/11/09 2       Requirements Team   100.00%                                                                                                                                                                                                
Release 2 Implementation 100% 70 4/12/09 4/22/09 59         Team   84.29%                                                                                                                                                                                                
Release 2 Testing 100% 20 4/22/09 4/25/09 38       Implementation Team   190.00%                                                                                                                                                                                                
Release 2 Bug Fixes 100% 10 4/25/09 4/27/09 45       Implementation Team   450.00%                                                                                                                                                                                                
Release 2 Deployment Instructions 100% 6 4/26/09 4/27/09 3       Bug Fixes Team   50.00%                                                                                                                                                                                                
Release 2 Create Source Package 100% 2 4/28/09 4/30/09 2         Team   100.00%                                                                                                                                                                                                
Release 2 Release Notes 100% 4 4/28/09 4/28/09 5       Bug Fixes Team   125.00%                                                                                                                                                                                                
  Project Poster Concept 100% 5 3/31/09 4/5/09 8 3/31/09 4/3/09     Rob   160.00%                                                                                                                                                                                                
  Preliminary Project Poster 100% 15 4/5/09 4/10/09 15 4/5/09 4/10/09     Rob   100.00%                                                                                                                                                                                                
  Final Poster Design 100% 5 4/11/09 4/21/09 3 4/11/09 4/21/09 Yes   Rob   60.00%                                                                                                                                                                                                
  Poster Session 100% 1 5/1/09 5/1/09 4 5/1/09 5/1/09 Yes   Team   400.00%                                                                                                                                                                                                
  Final Presentation: Coordinate With Sponser 100% 1 4/16/09 4/16/09 2         Team   200.00%                                                                                                                                                                                                
  Final Presentation Planning 100% 12 5/1/09 5/12/09 8         Team   66.67%                                                                                                                                                                                                
  Final Presentation 100% 2 5/12/09 5/12/09 1         Team   50.00%                                                                                                                                                                                                
  Spring Week 10 Post Mortem 100% 2 5/14/09 5/15/09 0     Yes   Team   0.00%                                                                                                                                                                                                
  Technical Report 100% 6 5/1/09 5/14/09 16     Yes       266.67%                                                                                                                                                                                                
  Spring Week 11 Final Deliverables 100% 5 5/20/09 5/20/09 0     Yes   Team   0.00%                                                                                                                                                                                                
Process Metric Tracking Process Metrics Tracking 1 100% 1 12/5/08 12/5/08 1 12/5/08 12/5/08     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 2 100% 1 12/12/08 12/12/08 1 12/12/08 12/12/08     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 3 100% 1 12/19/08 12/19/08 1 12/19/08 12/19/08     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 4 100% 1 1/9/09 1/9/09 1 1/9/09 1/9/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 5 100% 1 1/16/09 1/16/09 1 1/16/09 1/16/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 6 100% 1 1/23/09 1/23/09 1 1/23/09 1/23/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 7 100% 1 1/30/09 1/30/09 1 1/30/09 1/30/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 8 100% 1 2/6/09 2/6/09 1 2/6/09 2/6/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 9 100% 1 2/13/09 2/13/09 1 2/13/09 2/13/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 10 100% 1 2/20/09 2/20/09 1 2/20/09 2/20/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 11 100% 1 2/27/09 2/27/09 1 2/27/09 2/27/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 12 100% 1 3/13/09 3/13/09 1 3/13/09 3/13/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 13 100% 1 3/20/09 3/20/09 1 3/20/09 3/20/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 14 100% 1 3/27/09 3/27/09 1 3/27/09 3/27/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 15 100% 1 4/3/09 4/3/09 1 4/3/09 4/3/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 16 100% 1 4/10/09 4/10/09 1 4/10/09 4/10/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 17 100% 1 4/17/09 4/17/09 1 4/17/09 4/17/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 18 100% 1 4/24/09 4/24/09 1 4/24/09 4/24/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 19 100% 1 5/1/09 5/1/09 1 5/1/09 5/1/09     Team                                                                                                                                                                                                    
Process Metric Tracking Process Metrics Tracking 19 100% 1 5/8/09 5/8/09 1 5/8/09 5/8/09     Team