Severity Probability Team
low[1] low[2] Tom
medium[3] medium[4] Joe
high[5] high[6] Mark
Rob
Phil

[1]
tjs8938:
Not a big deal, project schedule will be impacted by less than one day
[2]
tjs8938:
This is not very likely to happen, 10-30% probability of occuring
[3]
tjs8938:
Moderately serious, may delay schedule by less than a week
[4]
tjs8938:
30-80% chance of occuring
[5]
tjs8938:
This is really bad, and could delay the schedule by at least a week
[6]
tjs8938:
very likely, 80-100% chance of occuring