Week |
Date |
Milestones |
1 |
December 1 |
Introduction to product &
sponsor |
2 |
December 8 |
Draft process & assign roles |
3 |
December 15 |
Produce synopsis, refine
process, meet with sponsor |
* |
December 22 |
Christmas Break |
4 |
January 5 |
Review progress & prepare
initial Software Requirements Specification (SRS) draft |
5 |
January 12 |
Prototype GUI v1.0 |
6 |
January 19 |
Complete SRS draft |
7 |
January 26 |
Inspect & deliver SRS v1.0 |
8 |
February 2 |
Prepare Software Design
Specification (SDS) Draft
|
9 |
February 9 |
Refine SRS v2.0 and
draft documents SDS v1.0, Quality Plan v1.0, and Test Plan v1.0 |
10 |
February 16 |
* |
February 23 |
Finals Week & Spring Break |
11 |
March 8 |
Draft Requirements Traceability
Matrix |
12 |
March 15 |
Refine Test Plan v1.0 & request
test data sets from Videk |
13 |
March 22 |
Begin Implementation & finalize
Test Plan v1.0 |
14 |
March 29 |
Finalize SDS v2.0 |
15 |
April 5 |
Deploy re-manufactured VDK-RIT
website |
16 |
April 12 |
Begin Test Plan Execution |
17 |
April 19 |
Finalize SDS v3.0 |
18 |
April 26 |
Finalize User Manual & Quick
Start card |
19 |
May 3 |
Demo Acceptance Tests, deliver
User Manual v1.0, finalize team poster board, draft Final Presentation |
20 |
May 10 |
Final Presentation, Write
summary paper, re-deploy latest VDK-RIT website |