VDK-RIT

 

Week

Date

Milestones

1

December 1

Introduction to product & sponsor
2

December 8

Draft process & assign roles
3

December 15

Produce synopsis, refine process, meet with sponsor
*

December 22

Christmas Break
4

January 5

Review progress & prepare initial Software Requirements Specification (SRS) draft
5

January 12

Prototype GUI v1.0
6 January 19 Complete SRS draft
7 January 26 Inspect & deliver SRS v1.0
8 February 2 Prepare Software Design Specification (SDS) Draft
9 February 9 Refine SRS v2.0 and draft documents SDS v1.0, Quality Plan v1.0, and Test Plan v1.0
10 February 16
* February 23 Finals Week & Spring Break
11 March 8 Draft Requirements Traceability Matrix
12 March 15 Refine Test Plan v1.0 & request test data sets from Videk
13 March 22 Begin Implementation & finalize Test Plan v1.0
14 March 29 Finalize SDS v2.0
15 April 5 Deploy re-manufactured VDK-RIT website
16 April 12 Begin Test Plan Execution
17 April 19 Finalize SDS v3.0
18 April 26 Finalize User Manual & Quick Start card
19 May 3 Demo Acceptance Tests, deliver User Manual v1.0, finalize team poster board, draft Final Presentation
20 May 10 Final Presentation, Write summary paper, re-deploy latest VDK-RIT website