Slippage chart - keep track how far behind or ahead we are
Sprint | Start/End | Slipped | Total |
---|---|---|---|
Application Setup Discovery | 9/29 - (10/6) 10/20 | +2 | +2 |
Application Setup Development | 10/6 (10/13) - 11/3 | 0 | 0 |
Purchase Process Discovery | 10/27 - 11/3 | 0 | 0 |
Documents Updated - For keeping documentation up to date with new code changes and new features/requested features.
Total Documents | Weekly Average | Adjusted Average |
---|---|---|
14 | 0.65 | 0.40 |
Week | Total Documents | Documents Updated |
---|---|---|
1 | 3 | 3 |
2 | 6 | 5 |
3 | 10 | 8 |
4 | 12 | 9 |
5 | 13 | 8 |
6 | 14 | 7 |
7 | 14 | 6 |
8 | 14 | 7 |
9 | 14 | 7 |
10 | 14 | 6 |
10 | 15 | 8 |