FARA Registry Project Schedule


Project Start:
Project Finish:
Tue 10/19/04
Fri 5/26/06


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
FARA Registry Project
199 days?Thu 12/1/05Fri 5/26/06 67%
2
Start Up and Planning
48.25 days?Thu 12/1/05Thu 1/12/06 100%
3
Conduct SU & P Workshop
1.13 daysThu 12/1/05Fri 12/2/05Whalen Michelle F100%
4
Finalize SU & P Documents\Components
6.75 daysSat 12/10/05Thu 12/15/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
5
Initial draft of SE department website
5.63 days?Tue 12/6/05Sat 12/10/05Coad Steve100%
6
Finish SE department website with artifcats
38.13 days?Sat 12/10/05Thu 1/12/06Coad Steve100%
7
Finalize Project plan, schedule, and process
21.94 days?Sat 12/10/05Wed 1/4/06Coad Steve,Morris Sandra,Simone Elaine,Rericha Tracy100%
8
Project Execution
191.13 days?Thu 12/1/05Fri 5/19/06 68%
9
Attend Project Meetings
191.13 days?Thu 12/1/05Fri 5/19/06Morris Sandra,Coad Steve,Rericha Tracy,Simone Elaine,Manos John,Farmer Jen,Whalen Michelle F,Wu Lei100%
10
Update Metrics on website
2 days?Thu 12/1/05Fri 12/2/05Coad Steve,Rericha Tracy20%
11
Analyze
15.75 daysTue 12/6/05Mon 12/19/05 100%
12
Define High Level Requirements
9 daysTue 12/6/05Tue 12/13/05Farmer Jen,Morris Sandra,Coad Steve,Simone Elaine,Rericha Tracy,Whalen Michelle F,Manos John100%
13
Analyze Phase Review \ Resolve Issues
1.13 daysMon 12/19/05Mon 12/19/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen100%
14
Obtain Customer Signoff on High Level Requirements
0.5 daysThu 12/15/05Thu 12/15/05Farmer Jen,Rericha Tracy100%
15
Define
73 days?Thu 12/1/05Fri 2/3/06 100%
16
Schedule JAD Sessions
1.13 daysSat 12/10/05Sat 12/10/05Rericha Tracy100%
17
Create a Solution Prototype
22.5 daysFri 12/9/05Thu 12/29/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
18
Conduct JAD Session to Determine Detailed Requirements
2.25 days?Fri 1/6/06Sat 1/7/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Whalen Michelle F,Manos John,Farmer Jen100%
19
Document Detailed Requirements
14.5 days?Thu 1/12/06Tue 1/24/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
20
Define Phase Review \ Resolve Issues
3.38 days?Tue 1/24/06Thu 1/26/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Whalen Michelle F,Manos John,Farmer Jen100%
21
Obtain Customer Signoff on Detailed Requirements
3.38 days?Tue 1/24/06Thu 1/26/06Farmer Jen,Rericha Tracy100%
22
Set up development environment
1 day?Mon 1/23/06Mon 1/23/06Coad Steve100%
23
Update Requirements Traceability document
3.38 days?Thu 1/26/06Sat 1/28/06Simone Elaine100%
24
Obtain Signoff on Requirements Traceability document
4.5 days?Tue 1/31/06Fri 2/3/06Rericha Tracy100%
25
Validate Project Schedule
1.13 days?Thu 1/26/06Thu 1/26/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
26
Validate Estimate
71.88 days?Thu 12/1/05Thu 2/2/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
27
Design
96.63 days?Thu 12/1/05Fri 2/24/06 96%
28
Learn development environment
1 day?Mon 1/30/06Mon 1/30/06Morris Sandra; Rericha Tracy; Simone Elaine0%
29
Modularity Document Signoff
37.13 days?Sat 1/7/06Wed 2/8/06Coad Steve,Rericha Tracy,Whalen Michelle F,Manos John100%
30
Create Initial Context, System and Architecture Diagrams
13.5 daysSun 1/1/06Thu 1/12/06Simone Elaine100%
31
Document Design
23.63 daysWed 1/25/06Tue 2/14/06Coad Steve,Rericha Tracy100%
32
Create Unit Test Cases
2.25 days?Sat 2/11/06Tue 2/14/06Morris Sandra,Simone Elaine100%
33
Design Phase Review / Resolve Issues
1.13 days?Thu 2/16/06Thu 2/16/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Farmer Jen,Whalen Michelle F100%
34
Unit Test Case Review / Resolve Issues
1.13 days?Fri 2/24/06Fri 2/24/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen100%
35
Resolve Issues and Re-Review Design
8.91 days?Fri 2/17/06Fri 2/24/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen100%
36
Resolve Issues and Re-Review Unit Test Cases
1 day?Fri 2/24/06Fri 2/24/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F0%
37
Complete interim evaluations
5.63 days?Mon 2/20/06Fri 2/24/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen,Wu Lei100%
38
Prepare for interim status project presentation
14.63 days?Fri 2/10/06Wed 2/22/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine100%
39
Database Signoff (part of Design)
0.25 days?Thu 12/1/05Thu 12/1/05Rericha Tracy,Coad Steve,Manos John,Whalen Michelle F0%
40
Design Signoff
0.5 days?Thu 12/1/05Thu 12/1/05Rericha Tracy,Farmer Jen,Whalen Michelle F,Manos John0%
41
Unit Test Cases Signoff
0.5 days?Thu 12/1/05Thu 12/1/05Rericha Tracy,Farmer Jen,Whalen Michelle F,Manos John0%
42
Model Office and Production Env Stand Up
1 day?Thu 12/1/05Thu 12/1/05Manos John0%
43
Produce
167.5 days?Thu 12/1/05Fri 4/28/06 0%
44
Validate Estimate and Project Schedule
4.5 days?Thu 2/23/06Sun 2/26/06Rericha Tracy0%
45
Create or Modify End User Procedures
18 days?Mon 3/6/06Tue 3/21/06Farmer Jen0%
46
Define and Document Needed System Test Cases
4.5 daysTue 2/28/06Fri 3/3/06Simone Elaine,Coad Steve0%
47
Define and Document User Acceptance Test (UAT) Cases
1 day?Thu 12/1/05Thu 12/1/05Farmer Jen0%
48
RIT Team Exam week
1 day?Thu 12/1/05Thu 12/1/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
49
RIT Spring break
1 day?Thu 12/1/05Thu 12/1/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
50
Review Evolutionary Prototpye with Customer (UI Review)
1 day?Thu 12/1/05Thu 12/1/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Farmer Jen,Manos John,Whalen Michelle F0%
51
.NET Training session
1 day?Thu 12/1/05Thu 12/1/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John0%
52
Module 1 Completion - Database
1 day?Fri 2/17/06Fri 2/17/06Coad Steve0%
53
Module 2 Completion - User Authentication/Login
1 day?Thu 12/1/05Thu 12/1/05Coad Steve0%
54
Module 3 Completion - Data Entry View
1 day?Thu 12/1/05Thu 12/1/05Morris Sandra0%
55
Module 4 Completion - Data Entry Logic
1 day?Thu 12/1/05Thu 12/1/05Simone Elaine0%
56
Module 5 Completion - Patient Update
1 day?Thu 12/1/05Thu 12/1/05Rericha Tracy0%
57
Module 6 Completion - Patient Review
1 day?Thu 12/1/05Thu 12/1/05Rericha Tracy0%
58
Module 7 Completion - Admin
1 day?Thu 12/1/05Thu 12/1/05Coad Steve0%
59
Module 8 Completion - Querying
1 day?Thu 12/1/05Thu 12/1/05Simone Elaine0%
60
Module 9 Completion - Registry auto-maint.
1 day?Thu 12/1/05Thu 12/1/05Coad Steve0%
61
Module 10 Completion - Static Site Content
1 day?Thu 12/1/05Thu 12/1/05Morris Sandra0%
62
Module 1 Review
0.11 days?Thu 12/1/05Thu 12/1/05Michelle Whalen,Tracy Rericha,Steve Coad,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman,Sherry Stone0%
63
Module 2, 3, and 4 Review
0.33 days?Thu 12/1/05Thu 12/1/05Sandy Morris,Elaine Simone,Steve Coad,Michelle Whalen,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman0%
64
Module 5, 6, and 7 Review
0.33 days?Thu 12/1/05Thu 12/1/05Steve Coad,Sandy Morris,Tracy Rericha,Michelle Whalen,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman0%
65
Module 8, 9, and 10 Review
0.3 days?Thu 12/1/05Thu 12/1/05Michelle Whalen,Elaine Simone,Steve Coad,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman,Rericha Tracy,Morris Sandra0%
66
Define and document a system testing plan
11.25 days?Tue 3/14/06Thu 3/23/06Simone Elaine0%
67
Define and document a UAT testing plan
22.5 days?Sat 3/4/06Thu 3/23/06Morris Sandra0%
68
Complete Produce (Code) \ execute unit test cases
65.25 days?Thu 2/23/06Fri 4/21/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
69
Produce Phase Review \ Resolve Issues
4.91 days?Mon 4/24/06Fri 4/28/06Steve Coad,Tracy Rericha,Lei Wu,Jen Farmer,John Manos,Michelle Whalen,Elaine Simone,Sandy Morris,Steve Sullivan,Steve Baiera,Marty Ohman0%
70
Testing Phase Review \ Resolve Issues
4.91 days?Mon 4/24/06Fri 4/28/06Steve Coad,Tracy Rericha,Lei Wu,Jen Farmer,John Manos,Michelle Whalen,Elaine Simone,Sandy Morris,Steve Sullivan,Steve Baiera,Marty Ohman0%
71
UAT Testing Review / Resolve Issues
1 day?Thu 12/1/05Thu 12/1/05 0%
72
Optimize
23.63 days?Wed 4/26/06Tue 5/16/06 0%
73
Create Release Implementation Plan
9 daysFri 4/28/06Fri 5/5/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
74
Build Environment For System Testing
7.88 days?Wed 4/26/06Tue 5/2/06Coad Steve0%
75
Execute System Testing \ Resolve Defects
11.25 days?Fri 4/28/06Sun 5/7/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
76
Build Environment For UAT Testing
3.38 days?Fri 5/5/06Sun 5/7/06Coad Steve0%
77
Execute UAT Testing \ Resolve Defects
10.13 days?Mon 5/8/06Tue 5/16/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
78
Obtain UAT Customer Signoff
1.13 days?Tue 5/16/06Tue 5/16/06Farmer Jen,Rericha Tracy0%
79
Implement
1.13 days?Fri 5/19/06Fri 5/19/06 0%
80
Execute Implementation Plan
1.13 days?Fri 5/19/06Fri 5/19/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
81
Project Closedown
199 days?Thu 12/1/05Fri 5/26/06 0%
82
Turn over final project deliverables and artifacts
1 day?Thu 12/1/05Thu 12/1/05Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
83
Prepare for final project presentation
9 days?Mon 5/15/06Mon 5/22/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
84
Prepare SE project poster
12.38 days?Mon 4/17/06Thu 4/27/06Morris Sandra,Rericha Tracy,Simone Elaine0%
85
Project Technical report
13.5 days?Mon 5/1/06Fri 5/12/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine0%
86
Complete final evaluations
13.5 days?Mon 5/15/06Fri 5/26/06Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen,Wu Lei0%