ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | FARA Registry Project | 199 days? | Thu 12/1/05 | Fri 5/26/06 | | 67% |
2 | Start Up and Planning | 48.25 days? | Thu 12/1/05 | Thu 1/12/06 | | 100% |
3 | Conduct SU & P Workshop | 1.13 days | Thu 12/1/05 | Fri 12/2/05 | Whalen Michelle F | 100% |
4 | Finalize SU & P Documents\Components | 6.75 days | Sat 12/10/05 | Thu 12/15/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
5 | Initial draft of SE department website | 5.63 days? | Tue 12/6/05 | Sat 12/10/05 | Coad Steve | 100% |
6 | Finish SE department website with artifcats | 38.13 days? | Sat 12/10/05 | Thu 1/12/06 | Coad Steve | 100% |
7 | Finalize Project plan, schedule, and process | 21.94 days? | Sat 12/10/05 | Wed 1/4/06 | Coad Steve,Morris Sandra,Simone Elaine,Rericha Tracy | 100% |
8 | Project Execution | 191.13 days? | Thu 12/1/05 | Fri 5/19/06 | | 68% |
9 | Attend Project Meetings | 191.13 days? | Thu 12/1/05 | Fri 5/19/06 | Morris Sandra,Coad Steve,Rericha Tracy,Simone Elaine,Manos John,Farmer Jen,Whalen Michelle F,Wu Lei | 100% |
10 | Update Metrics on website | 2 days? | Thu 12/1/05 | Fri 12/2/05 | Coad Steve,Rericha Tracy | 20% |
11 | Analyze | 15.75 days | Tue 12/6/05 | Mon 12/19/05 | | 100% |
12 | Define High Level Requirements | 9 days | Tue 12/6/05 | Tue 12/13/05 | Farmer Jen,Morris Sandra,Coad Steve,Simone Elaine,Rericha Tracy,Whalen Michelle F,Manos John | 100% |
13 | Analyze Phase Review \ Resolve Issues | 1.13 days | Mon 12/19/05 | Mon 12/19/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen | 100% |
14 | Obtain Customer Signoff on High Level Requirements | 0.5 days | Thu 12/15/05 | Thu 12/15/05 | Farmer Jen,Rericha Tracy | 100% |
15 | Define | 73 days? | Thu 12/1/05 | Fri 2/3/06 | | 100% |
16 | Schedule JAD Sessions | 1.13 days | Sat 12/10/05 | Sat 12/10/05 | Rericha Tracy | 100% |
17 | Create a Solution Prototype | 22.5 days | Fri 12/9/05 | Thu 12/29/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
18 | Conduct JAD Session to Determine Detailed Requirements | 2.25 days? | Fri 1/6/06 | Sat 1/7/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Whalen Michelle F,Manos John,Farmer Jen | 100% |
19 | Document Detailed Requirements | 14.5 days? | Thu 1/12/06 | Tue 1/24/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
20 | Define Phase Review \ Resolve Issues | 3.38 days? | Tue 1/24/06 | Thu 1/26/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Whalen Michelle F,Manos John,Farmer Jen | 100% |
21 | Obtain Customer Signoff on Detailed Requirements | 3.38 days? | Tue 1/24/06 | Thu 1/26/06 | Farmer Jen,Rericha Tracy | 100% |
22 | Set up development environment | 1 day? | Mon 1/23/06 | Mon 1/23/06 | Coad Steve | 100% |
23 | Update Requirements Traceability document | 3.38 days? | Thu 1/26/06 | Sat 1/28/06 | Simone Elaine | 100% |
24 | Obtain Signoff on Requirements Traceability document | 4.5 days? | Tue 1/31/06 | Fri 2/3/06 | Rericha Tracy | 100% |
25 | Validate Project Schedule | 1.13 days? | Thu 1/26/06 | Thu 1/26/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
26 | Validate Estimate | 71.88 days? | Thu 12/1/05 | Thu 2/2/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
27 | Design | 96.63 days? | Thu 12/1/05 | Fri 2/24/06 | | 96% |
28 | Learn development environment | 1 day? | Mon 1/30/06 | Mon 1/30/06 | Morris Sandra; Rericha Tracy; Simone Elaine | 0% |
29 | Modularity Document Signoff | 37.13 days? | Sat 1/7/06 | Wed 2/8/06 | Coad Steve,Rericha Tracy,Whalen Michelle F,Manos John | 100% |
30 | Create Initial Context, System and Architecture Diagrams | 13.5 days | Sun 1/1/06 | Thu 1/12/06 | Simone Elaine | 100% |
31 | Document Design | 23.63 days | Wed 1/25/06 | Tue 2/14/06 | Coad Steve,Rericha Tracy | 100% |
32 | Create Unit Test Cases | 2.25 days? | Sat 2/11/06 | Tue 2/14/06 | Morris Sandra,Simone Elaine | 100% |
33 | Design Phase Review / Resolve Issues | 1.13 days? | Thu 2/16/06 | Thu 2/16/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Farmer Jen,Whalen Michelle F | 100% |
34 | Unit Test Case Review / Resolve Issues | 1.13 days? | Fri 2/24/06 | Fri 2/24/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen | 100% |
35 | Resolve Issues and Re-Review Design | 8.91 days? | Fri 2/17/06 | Fri 2/24/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen | 100% |
36 | Resolve Issues and Re-Review Unit Test Cases | 1 day? | Fri 2/24/06 | Fri 2/24/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F | 0% |
37 | Complete interim evaluations | 5.63 days? | Mon 2/20/06 | Fri 2/24/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen,Wu Lei | 100% |
38 | Prepare for interim status project presentation | 14.63 days? | Fri 2/10/06 | Wed 2/22/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 100% |
39 | Database Signoff (part of Design) | 0.25 days? | Thu 12/1/05 | Thu 12/1/05 | Rericha Tracy,Coad Steve,Manos John,Whalen Michelle F | 0% |
40 | Design Signoff | 0.5 days? | Thu 12/1/05 | Thu 12/1/05 | Rericha Tracy,Farmer Jen,Whalen Michelle F,Manos John | 0% |
41 | Unit Test Cases Signoff | 0.5 days? | Thu 12/1/05 | Thu 12/1/05 | Rericha Tracy,Farmer Jen,Whalen Michelle F,Manos John | 0% |
42 | Model Office and Production Env Stand Up | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Manos John | 0% |
43 | Produce | 167.5 days? | Thu 12/1/05 | Fri 4/28/06 | | 0% |
44 | Validate Estimate and Project Schedule | 4.5 days? | Thu 2/23/06 | Sun 2/26/06 | Rericha Tracy | 0% |
45 | Create or Modify End User Procedures | 18 days? | Mon 3/6/06 | Tue 3/21/06 | Farmer Jen | 0% |
46 | Define and Document Needed System Test Cases | 4.5 days | Tue 2/28/06 | Fri 3/3/06 | Simone Elaine,Coad Steve | 0% |
47 | Define and Document User Acceptance Test (UAT) Cases | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Farmer Jen | 0% |
48 | RIT Team Exam week | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
49 | RIT Spring break | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
50 | Review Evolutionary Prototpye with Customer (UI Review) | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Farmer Jen,Manos John,Whalen Michelle F | 0% |
51 | .NET Training session | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John | 0% |
52 | Module 1 Completion - Database | 1 day? | Fri 2/17/06 | Fri 2/17/06 | Coad Steve | 0% |
53 | Module 2 Completion - User Authentication/Login | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve | 0% |
54 | Module 3 Completion - Data Entry View | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Morris Sandra | 0% |
55 | Module 4 Completion - Data Entry Logic | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Simone Elaine | 0% |
56 | Module 5 Completion - Patient Update | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Rericha Tracy | 0% |
57 | Module 6 Completion - Patient Review | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Rericha Tracy | 0% |
58 | Module 7 Completion - Admin | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve | 0% |
59 | Module 8 Completion - Querying | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Simone Elaine | 0% |
60 | Module 9 Completion - Registry auto-maint. | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve | 0% |
61 | Module 10 Completion - Static Site Content | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Morris Sandra | 0% |
62 | Module 1 Review | 0.11 days? | Thu 12/1/05 | Thu 12/1/05 | Michelle Whalen,Tracy Rericha,Steve Coad,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman,Sherry Stone | 0% |
63 | Module 2, 3, and 4 Review | 0.33 days? | Thu 12/1/05 | Thu 12/1/05 | Sandy Morris,Elaine Simone,Steve Coad,Michelle Whalen,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman | 0% |
64 | Module 5, 6, and 7 Review | 0.33 days? | Thu 12/1/05 | Thu 12/1/05 | Steve Coad,Sandy Morris,Tracy Rericha,Michelle Whalen,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman | 0% |
65 | Module 8, 9, and 10 Review | 0.3 days? | Thu 12/1/05 | Thu 12/1/05 | Michelle Whalen,Elaine Simone,Steve Coad,John Manos,Lei Wu,Steve Sullivan,Steve Baiera,Marty Ohman,Rericha Tracy,Morris Sandra | 0% |
66 | Define and document a system testing plan | 11.25 days? | Tue 3/14/06 | Thu 3/23/06 | Simone Elaine | 0% |
67 | Define and document a UAT testing plan | 22.5 days? | Sat 3/4/06 | Thu 3/23/06 | Morris Sandra | 0% |
68 | Complete Produce (Code) \ execute unit test cases | 65.25 days? | Thu 2/23/06 | Fri 4/21/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
69 | Produce Phase Review \ Resolve Issues | 4.91 days? | Mon 4/24/06 | Fri 4/28/06 | Steve Coad,Tracy Rericha,Lei Wu,Jen Farmer,John Manos,Michelle Whalen,Elaine Simone,Sandy Morris,Steve Sullivan,Steve Baiera,Marty Ohman | 0% |
70 | Testing Phase Review \ Resolve Issues | 4.91 days? | Mon 4/24/06 | Fri 4/28/06 | Steve Coad,Tracy Rericha,Lei Wu,Jen Farmer,John Manos,Michelle Whalen,Elaine Simone,Sandy Morris,Steve Sullivan,Steve Baiera,Marty Ohman | 0% |
71 | UAT Testing Review / Resolve Issues | 1 day? | Thu 12/1/05 | Thu 12/1/05 | | 0% |
72 | Optimize | 23.63 days? | Wed 4/26/06 | Tue 5/16/06 | | 0% |
73 | Create Release Implementation Plan | 9 days | Fri 4/28/06 | Fri 5/5/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
74 | Build Environment For System Testing | 7.88 days? | Wed 4/26/06 | Tue 5/2/06 | Coad Steve | 0% |
75 | Execute System Testing \ Resolve Defects | 11.25 days? | Fri 4/28/06 | Sun 5/7/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
76 | Build Environment For UAT Testing | 3.38 days? | Fri 5/5/06 | Sun 5/7/06 | Coad Steve | 0% |
77 | Execute UAT Testing \ Resolve Defects | 10.13 days? | Mon 5/8/06 | Tue 5/16/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
78 | Obtain UAT Customer Signoff | 1.13 days? | Tue 5/16/06 | Tue 5/16/06 | Farmer Jen,Rericha Tracy | 0% |
79 | Implement | 1.13 days? | Fri 5/19/06 | Fri 5/19/06 | | 0% |
80 | Execute Implementation Plan | 1.13 days? | Fri 5/19/06 | Fri 5/19/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
81 | Project Closedown | 199 days? | Thu 12/1/05 | Fri 5/26/06 | | 0% |
82 | Turn over final project deliverables and artifacts | 1 day? | Thu 12/1/05 | Thu 12/1/05 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
83 | Prepare for final project presentation | 9 days? | Mon 5/15/06 | Mon 5/22/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
84 | Prepare SE project poster | 12.38 days? | Mon 4/17/06 | Thu 4/27/06 | Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
85 | Project Technical report | 13.5 days? | Mon 5/1/06 | Fri 5/12/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine | 0% |
86 | Complete final evaluations | 13.5 days? | Mon 5/15/06 | Fri 5/26/06 | Coad Steve,Morris Sandra,Rericha Tracy,Simone Elaine,Manos John,Whalen Michelle F,Farmer Jen,Wu Lei | 0% |