- Saturday scrum will be held online this week, since many members will be
out of town
- Divided sections of project plan amongst group members. Brian will
combine these sections into the first draft document.
- Jira is another issue tracking tool, and may be an option if the setup
for Bugzilla is too complex on our server.
- Tasks for weekend
-Mark will work on measurements and metrics section in project plan
-Joe will work on project plan starting after our Saturday scrum
-Brian will combine individual contributions for project plan into the main
project plan document
-Move Dec 16 2007 XSD issue to low priority
-Rob will send out draft 1 of our project plan to the client on Sunday
|