  • The poster is nearly finished. The team has received feedback from both the client and from our faculty coach on problem areas.
     
  • There will be no on-campus meeting with the client prior to the final presentation. Carlyle can make it to our final presentation.
     
  • Webster has received product release 2 and was impressed. Several defects were found that the team hadn't noticed, though, and these have been input into our defect tracker.
     
  • Tasks for next meeting:
    -Finish poster
    -Product release 3
    -Fix/reproduce defects that Webster found with product release 2