Cycle One
Project Dates:  December 2, 2003 - February 2, 2004
Phase Completion date Deliverable
Kickoff 12/2/2003 AFRL Project Kickoff Meeting
Kickoff 12/10/2003 AFRL Initial Requirements Meeting
Kickoff 12/18/2003 Team Responsibilities Document
Kickoff 12/18/2003 Kickoff Document
Kickoff 12/18/2003 Initial Planning Document
Kickoff 12/18/2003 Initial Process Document
Kickoff 12/18/2003 Risks and Alternatives Document
Requirements 1/7/2004 Elicitation Questions
Requirements 1/8/2004 AFRL Elicitation Meeting
Requirements 1/15/2004 Initial Requirements Document
Requirements 1/16/2004 Dynamic Code Loading Prototype
Requirements 1/19/2004 Initial Architectural Diagram
Requirements 1/20/2004 Requirements Inspection
Design 1/23/2004 Initial Manipulation/Plug-in Class Diagram
Design 1/23/2004 Initial Manipulation/Plug-in Sequence Diagrams
Implementation 1/26/2004 User Interface Prototype
Implementation 1/26/2004 Functional Prototype
Implementation 1/27/2004 One-Click Deployment of ESDI
Documentation 1/27/2004 Installation Documentation
Testing 1/27/2004 Test Tool Development/Research
Testing 1/28/2004 Code Inspection
Testing 1/29/2004 Initial Operational Test Scenarios
Testing 1/29/2004 Initial Test Plan
Testing 1/30/2004 Prototype Testing
Postmortem 2/2/2004 Cycle 1 Postmortem Document
Cycle Two
Project Dates:  February 6, 2004 - March 30, 2004
Phase Completion date Deliverable
Kickoff 2/6/2004 Cycle 2 Plan Update
Kickoff 2/6/2004 Cycle 2 Process Update
Requirements 2/9/2004 Complete Requirements Document
Requirements 2/10/2004 Requirements Inspection
Design 2/13/2004 System Class Diagram
Design 2/13/2004 System Sequence Diagrams
Implementation 2/27/2004 System Integration (Baseline)
Documentation 3/4/2004 Initial User's Manual
Documentation 3/4/2004 Initial Developer's Manual
Testing 3/9/2004 Complete Test Plan
Testing 3/12/2004 Initiate System Test of ESDI
Testing 3/21/2004 Critical Bugs Fixed;  All Bugs Recorded
Testing 3/23/2004 Acceptance Test of ESDI (Trial Install)
Postmortem 3/26/2004 Cycle 2 Postmortem Document
Postmortem 3/30/2004 First Quarter Presentation
Cycle Three
Project Dates:  April 2, 2004 - May 19, 2004
Phase Completion date Deliverable
Kickoff 4/2/2004 Cycle 3 Plan Update
Kickoff 4/2/2004 Cycle 3 Process Update
Testing 4/23/2004 All bugs resolved (fixed or deferred)
Documentation 5/7/2004 Complete User's Manual
Documentation 5/7/2004 Complete Developer's Manual
Postmortem 5/14/2004 Conference Short-Paper
Postmortem 5/17/2004 Presentation to AFRL - Final Project/Product
Postmortem 5/18/2004 Project Poster
Postmortem 5/19/2004 Second Quarter Presentation