Home | Project Overview | People | Process | Planning | Prototypes | Documentation | Task Tracker |
Cycle One |
Project Dates: December 2, 2003 - February 2, 2004 | ||
Phase | Completion date | Deliverable |
Kickoff | 12/2/2003 | AFRL Project Kickoff Meeting |
Kickoff | 12/10/2003 | AFRL Initial Requirements Meeting |
Kickoff | 12/18/2003 | Team Responsibilities Document |
Kickoff | 12/18/2003 | Kickoff Document |
Kickoff | 12/18/2003 | Initial Planning Document |
Kickoff | 12/18/2003 | Initial Process Document |
Kickoff | 12/18/2003 | Risks and Alternatives Document |
Requirements | 1/7/2004 | Elicitation Questions |
Requirements | 1/8/2004 | AFRL Elicitation Meeting |
Requirements | 1/15/2004 | Initial Requirements Document |
Requirements | 1/16/2004 | Dynamic Code Loading Prototype |
Requirements | 1/19/2004 | Initial Architectural Diagram |
Requirements | 1/20/2004 | Requirements Inspection |
Design | 1/23/2004 | Initial Manipulation/Plug-in Class Diagram |
Design | 1/23/2004 | Initial Manipulation/Plug-in Sequence Diagrams |
Implementation | 1/26/2004 | User Interface Prototype |
Implementation | 1/26/2004 | Functional Prototype |
Implementation | 1/27/2004 | One-Click Deployment of ESDI |
Documentation | 1/27/2004 | Installation Documentation |
Testing | 1/27/2004 | Test Tool Development/Research |
Testing | 1/28/2004 | Code Inspection |
Testing | 1/29/2004 | Initial Operational Test Scenarios |
Testing | 1/29/2004 | Initial Test Plan |
Testing | 1/30/2004 | Prototype Testing |
Postmortem | 2/2/2004 | Cycle 1 Postmortem Document |
Cycle Two |
Project Dates: February 6, 2004 - March 30, 2004 | ||
Phase | Completion date | Deliverable |
Kickoff | 2/6/2004 | Cycle 2 Plan Update |
Kickoff | 2/6/2004 | Cycle 2 Process Update |
Requirements | 2/9/2004 | Complete Requirements Document |
Requirements | 2/10/2004 | Requirements Inspection |
Design | 2/13/2004 | System Class Diagram |
Design | 2/13/2004 | System Sequence Diagrams |
Implementation | 2/27/2004 | System Integration (Baseline) |
Documentation | 3/4/2004 | Initial User's Manual |
Documentation | 3/4/2004 | Initial Developer's Manual |
Testing | 3/9/2004 | Complete Test Plan |
Testing | 3/12/2004 | Initiate System Test of ESDI |
Testing | 3/21/2004 | Critical Bugs Fixed; All Bugs Recorded |
Testing | 3/23/2004 | Acceptance Test of ESDI (Trial Install) |
Postmortem | 3/26/2004 | Cycle 2 Postmortem Document |
Postmortem | 3/30/2004 | First Quarter Presentation |
Cycle Three |
Project Dates: April 2, 2004 - May 19, 2004 | ||
Phase | Completion date | Deliverable |
Kickoff | 4/2/2004 | Cycle 3 Plan Update |
Kickoff | 4/2/2004 | Cycle 3 Process Update |
Testing | 4/23/2004 | All bugs resolved (fixed or deferred) |
Documentation | 5/7/2004 | Complete User's Manual |
Documentation | 5/7/2004 | Complete Developer's Manual |
Postmortem | 5/14/2004 | Conference Short-Paper |
Postmortem | 5/17/2004 | Presentation to AFRL - Final Project/Product |
Postmortem | 5/18/2004 | Project Poster |
Postmortem | 5/19/2004 | Second Quarter Presentation |