Project Timeline

The Project Timeline shows an overall view of the schedule for the activities of the project. It reflects a waterfall methodology and indicates the dates each phase will begin and end.

The project is broken down into sections corresponding to Bluetooth Profiles including BPP, OPP, FTP, and OBEX. In the timeline each section of the project is broken out separately to indicate where its development is in relation to the other sections. The timeline does not indicate specific deliverable dates.

When the timeline is updated the new version will be included at the top of the list. The timeline is used to show the current overall project and will not be used to indicate schedule slippage.

Project Timeline 02/15/05

Project Timeline 01/28/05

Project Timeline 01/19/05

Related Documents:

To view deliverable due dates and schedule slippage see the Gantt Chart

For a report of schedule slippage per week and overall total see Schedule Slippage Metric.